Darrington Library Construction Updates

Inch by inch, one foot at a time, we are one step closer to your reimagined library. We are taking measure of our progress and will provide you with updates on the construction progress and exciting new features.

Construction as of July 19, 2023


  • Glass storefront walls at the library entrance were installed.
  • The folding glass wall providing an opening to the outdoor space was installed.
  • Wood cabinetry is being installed, including in the enhanced children’s area.
  • The exterior of the building was trimmed.
  • Flooring will be installed next week.

Construction Highlights as of June 20, 2023

  • Painted the outside of the library a deep green, Sherwin Williams' "Ripe Olive."
  • Poured new asphalt for the parking lot.
  • Poured new sidewalk and entryway concrete.
  • Laid pavers in the new outdoor space and planted a kousa dogwood tree.
  • Installed skylight above entry lobby to create a brighter space.
  • Framing and drywall completed, and interior painting is started, including the new community study room.